Refurbishment works have been completed on an automotive workshop in need of repair following a fire in one area. Having completed the demolition and enabling works package in the Summer of 2023, Abbott were appointed to continue with works on the full repair and refurbishment to allow the college to make full use of the facility.
Phase one of the works focused on the damaged section of the building, approximately two-thirds of the building footprint. A new steel frame roof heightened the building by roughly 1m. The new roof light layout combined with added height provides better space utilisation and higher level of natural lighting.
The undamaged half of the building continued to operate during phase one, something the site team had to meticulously navigate, being so close to the students and staff, ensuring their safety, and keeping disruption to a minimum.
Phase two of the works comprised the same roof/frame/roof light replacement to match and seamlessly connect to the phase one section of the building.
The entrance area was remodelled to provide toilet facilities, a locker room and a teaching space. The existing automotive workshop area was completely refurbished to replicate what was there previously, including replacement windows, escape doors, and a roller shutter door.
The entire project was completed in 12 weeks ahead of programme and was under budget.